Current Status of the Project:
- We have continued reviewing methods that can be used to measure flow of liquid and evaluating how these methods could be adapted to our purposes.
- We met with our client, Brad Clay, to brainstorm possible solutions and to pick out our top solution
- Literature has been gathered on these methods
- We worked on our presentation and finished up our progress report
Work Planned for Next Week:
- Some design sketches will be started on (for TDR, our chosen method)
- Initial risk analysis will be performed
- Meet with our client, Brad, to discuss next steps as well as to pick up parts from him
- Brad is also providing us with certain equipment (Foley catheter, urine bag, etc.)